“As an ambitious and hard-working individual, I am often recognized for my commitment and ability by highly respected companies. I handle multiple tasks on a daily basis competently, working well under the pressure. Frequent acknowledgment of my contribution from senior management illustrates my potential value to your company. I would welcome the opportunity to discuss my suitability in more detail.”
Resume created on DoYouBuzz
  • Budget FTY 18-19 (EVA)
  • Scheduling monthly programme (Flyover & underpass) and monitoring the same on daily basis.
  • Preparation of work progress records & financial reports.
  • Preparation of Master schedule (L1) then day wise activity breakup accordingly. (upto L4) Level.
  • Monitoring the works & cost as per the budget, shortfall analysis (cost variance) if any deviation found. (communication to HO)
  • Preparation of detailed Progress plan Including Schedule & Cost.
  • Identification of related to cost risk & its mitigation.
  • Comparison of scope , quantities Vs actual executed.
  • Daily, weekly & monthly reports preparation
  • Assistance to Site team & Manager Projects.
  • Road works on flyover , Over deck slab & Underpass (2300m)
  • Road works Sub base, base, DBM , BM works
  • Preparation of Budget.(FTY 17-18)
  • Preparation of schedules (L4) and Monitoring them like Entry Exits Structure and all Finishing Works.
  • Planned Vs Actual Analysis, and monitoring the difference between them in cost as well as in time.
  • Preparation of various reports like Daily, Weekly and Monthly Financial and Progress Reports.
  • Preparation and approval of Method Statement for various activities of the Project.
  • Identification of risk and its mitigation.
  • Preparation of Presentations for Management review.
  • Preparation of Major Material Reconciliation for the Project on Monthly Basis
  • Quantity estimation of structural steel,Excavation, Concrete, Reinforcement,Shuttering, Finishing Items (Granite, False Ceiling, Cladding etc) for all the entry exits and Box Pushing.
  • Calculated all subcontractor Direct and indirect project costs.
  • Interface Coordination :- Interfacing between Site - Client - System contractor - Finishing Agencies and succeeding contractor (ITD DMRC CC-32)
  • Interfacing with Subcon regarding design and Inspection of PEB Structure, and further interfacing with system contractor during erection.
  • Interfacing regarding box pushing with Subcon - Client - Site and Utility Agencies.
  • Preparation of bills of System contractor ie Crane Hire, Electricity Etc.
  • Preparation of Bills of Sub Contractor & System Contractor.
  • Preparing Monthly Targets, Major Material Requirements for all the sites, Action Plans to Achieve the targets and Shortfall analysis.
  • Road Works (Restoration).(2000m)
Detailed Description
  • DMRC Project
  • Janakpuri to Palam
  • Preparation of Monthly bills of Sub Contractor.
  • Calculation of material quantity ie R/F , Shuttering & Str. Steel.
  • Client And Contractor Billing
  • Preparation of Major Material Reconciliation for the Project on Monthly Basis
  • Planning of material as per resources.
  • Interface Coordination :- Interfacing between Site - Client - System contractor - Finishing Agencies.
  • Submission of MPR & Site Photographs to client as per contractual requirement.
  • Preparation of various reports like Daily, Weekly and Monthly Financial and Progress Reports.
  • Approach Road works (900m)
  • Cal. of Shuttering material.
  • Site Inspection
  • Preparation of BBS & Cal. of steel quantity.
  • Checking of Reinforcement as per drawing.